  • Vessel’s Return: The Floating Storage Regasification Unit (FSRU) vessel, LNG Croatia, has returned to its terminal on the island of Krk after a 55-day absence.
  • Major Upgrades: The vessel underwent a crucial five-year class renewal and was fitted with a new, advanced regasification module.
  • Commissioning Phase: A period of intensive preparation, testing, and inspection is now underway for both the FSRU and the onshore terminal facilities.
  • Target Relaunch: The terminal is aiming for a safe and reliable restart of commercial operations on October 26, 2025.

FSRU LNG Croatia Returns Home to Krk Terminal

After a 55-day mission crucial for its modernization, the FSRU vessel LNG Croatia has successfully returned to its strategic post at the LNG terminal in Omišalj, located on the island of Krk. The vessel’s return marks a significant milestone in securing Croatia’s long-term energy infrastructure.

A Critical 55-Day Mission for Upgrades

The vessel’s extended absence was dedicated to two primary objectives essential for its continued operation and efficiency. The first was the completion of its five-year class renewal, a comprehensive inspection and maintenance process that ensures the vessel meets strict international safety and operational standards.

The second, and more significant, development was the installation and implementation of a new regasification module. This key upgrade enhances the FSRU’s capacity and efficiency in converting liquefied natural gas (LNG) back into its gaseous state, directly improving the terminal’s output and reliability.

The Road to Recommissioning

With the FSRU now safely berthed, the operational team has commenced the final phase of preparations before it re-enters service. This period involves meticulous testing and final inspections of both the upgraded vessel and the corresponding onshore components of the terminal. The primary goal is to ensure seamless integration and to guarantee a safe and dependable start of commercial operations.

Countdown to Commercial Operation

All efforts are now focused on the target date of October 26, 2025, when the LNG Croatia is scheduled to resume full commercial activity. The successful recommissioning of this vessel is vital not only for Croatia but for the wider region, reinforcing the nation’s role as a key player in European energy security.